Posts

Sao Paulo Metropolitan Beltway

The São Paulo state government is expected to auction on Wednesday the northern stretch of Rodoanel Metropolitano. With the new concession, the expectation is to finally conclude the construction of the beltway of Greater São Paulo, which began in 1998.

The contract provides for R$3 billion in investments over 31 years. Of this amount, R$1.7 billion will be used to complete the work – about 25% of the northern stretch, which is 44 km long and passes through São Paulo, Guarulhos and Arujá, has yet to be built. The beltway is expected to be fully delivered in two years.

The project will be a public-private partnership (PPP), a model in which the government contributes part of the funds. In total, the state of São Paulo is prepared to inject around R$2 billion (excluding monetary corrections): in addition to an initial contribution for the work, of up to R$876.7 million, the project includes annual payments to the concessionaire of up to R$41.65 million.

However, the amount disbursed by the government may fall, depending on the level of competition. The winner will be the one offering the biggest discount on the public contribution. According to the public notice, the interested parties must propose a discount on the value of the annual payments. If this reaches 100%, the discount on the initial contribution becomes valid.

The perception in the market is that there will be interest in the project, despite the challenging scenario. Traditional operators such as CCR, Ecorodovias and Pátria are seen as candidates.

Ecorodovias has not cited Rodoanel on its list of priorities. However, the group is considered a possible interested party because it won the first auction of the stretch, held in 2018. At the time, the bid notice only provided for the operation of the road, since the work would be completed by the state government. In the end, however, the contract was not signed and the model was changed.

CCR already operates the Rodoanel Oeste (west stretch) concession and, therefore, reportedly has synergies with the northern stretch. Another company in this situation is Bertin group’s SP Mar, which operates the south and east stretches of the beltway. Although the concessionaire is under protection from creditors, analysts do not rule out an attempt to dispute the asset through a consortium.

Ecorodovias and Pátria declined to comment. SP Mar says it has not made a decision and is awaiting a response from shareholders and investors. CCR did not reply to a request for comment.

“The expectation is for competition. Although it is not common in São Paulo, the PPP model for highways is well seen among companies, due to the state’s history of being a good payer and other successful experiences with projects in this model,” said Rafael Vanzella, a partner at law firm Machado Meyer.

For Eduardo Ramires, a partner at Manesco Advogados, a limited dispute is expected. He points out that, besides the project’s challenges, such as expropriations and environmental issues, there is an unfavorable situation aggravated by the war in Ukraine that puts pressure on the construction costs and generates uncertainty regarding the highway’s traffic. In addition, he highlights the risk for the new concessionaire of taking over a work largely built by third parties. “The operator assumes responsibility for the work already done. This succession always raises concern,” he said.

In relation to this point, the São Paulo state government has highlighted the hiring of an independent report prepared by Instituto de Pesquisas Tecnológicas (IPT) on the state of the works. In addition, in a period of six months after the signing of the contract, an independent firm will be able to point out possible divergences in relation to the structure, which will be taken to a technical commission.

The São Paulo state government has been trying to get the Rodoanel Norte highway off the drawing board for at least 10 years, during which time more than R$7 billion have already been spent. In addition, the project was targeted by the anti-corruption task force Car-Wash Operation and marked by investigations for suspected embezzlement.

In 2012, when the first tender for the Rodoanel Norte was held, the project was divided into six lots, which were won by construction companies such as Mendes Júnior, OAS, Acciona and Construcap. In view of the delays, the six contracts were terminated – three of them at the end of 2018, and the others in May 2019.

Besides the inclusion of the work in the contract, another point of attention in the project is the inclusion of the “free flow” collection system (no toll plazas and payment calculated by kilometers driven), still innovative in the country, said André Bogossian, a lawyer with Stocche Forbes.

“There are doubts about how the payment and default will be, because there is no culture of automatic payment in the country,” he said. He highlights that, to mitigate this uncertainty, the São Paulo state government included risk sharing mechanisms in the call for bids.

Source: Valor International

https://valorinternational.globo.com